Abstract
This study examined the performance appraisal of Construction Project Managers (CPMs) in Accra, Ghana, focusing on four key factors: inadequate resource allocation, weak monitoring and evaluation (M&E) frameworks, the absence of standardized performance appraisal metrics, and low adoption of contemporary project management technologies. A quantitative, descriptive cross-sectional research design was employed, with structured survey questionnaires administered to 104 respondents comprising CPMs, clients, contractors, site engineers, and consultants. Descriptive statistics, Pearson correlation, simple linear regression, and multiple regression analysis were used to analyse the data using SPSS version 27. The Cronbach's Alpha reliability coefficient was 0.958, confirming exceptional instrument consistency. Results reveal that delayed fund disbursement (M = 4.10), reactive monitoring practices (M = 3.86), inadequate evaluator training (M = 3.73), and budgetary constraints on technology adoption (M = 3.83) are the most critical sub-factors undermining CPM performance. Regression analyses indicate that inadequate resource allocation explains 40.0% (R² = .400), weak M&E frameworks 57.8% (R² = .578), absence of standardized appraisal metrics 28.7% (R² = .287), and low technology adoption 61.0% (R² = .610) of the variance in performance outcomes. The combined multiple regression model yielded R² = .740, explaining 74.0% of total performance variance. The study recommends continuous professional development, structured M&E frameworks, standardized KPI-based appraisal systems, and targeted policy incentives for technology adoption to enhance CPM performance and improve project delivery outcomes in Ghana's construction sector.References
Abdul-Rahman, H., Takim, R., & Min, W. S. (2009). Financial-related causes contributing to project delays. Journal of Retail & Leisure Property, 8(3), 225–238. https://doi.org/10.1057/rlp.2009.11
Aguinis, H. (2019). Performance management for dummies. Hoboken, NJ: Wiley.
Ahadzie, D. K., Proverbs, D. G., & Olomolaiye, P. (2008a). Towards developing competency-based measures for project managers in mass house building projects in developing countries. Construction Management and Economics, 26(1), 15–29. https://doi.org/10.1080/01446190701793651
Ahadzie, D. K., Proverbs, D. G., & Olomolaiye, P. (2008b). Critical success criteria for mass house building projects in developing countries. International Journal of Project Management, 26(6), 675–687. https://doi.org/10.1016/j.ijproman.2007.09.006
Ajayi, T. O., Daramola, O. T., & Adhuze, O. O. (2024). Cost management evolution in building projects: A review of innovations and challenges. International Journal of Research and Innovation in Applied Science, IX(IX), 80–95. https://doi.org/10.51584/IJRIAS.2024.909009
Alias, Z., Zawawi, E. M. A., Yusof, K., & Aris, N. M. (2014). Determining critical success factors of project management practice: A conceptual framework. Procedia - Social and Behavioral Sciences, 153, 61–69.
Amoatey, C. T., Ankrah, A. N. O., Kwofie, T. E., & Famiyeh, S. (2015). Analysing delay causes and effects in Ghanaian state housing construction projects. International Journal of Managing Projects in Business, 8(1), 198–214.
Armstrong, M., & Baron, A. (2005). Managing performance: Performance management in action. London: Chartered Institute of Personnel and Development.
Aubry, M., Hobbs, B., Müller, R., & Blomquist, T. (2011). Identifying forces driving PMO changes. Project Management Journal, 42(6), 40–52. https://doi.org/10.1002/pmj.20271
Augustine, S. T., Aaron, D. R., et al. (2025). Cost overruns in public sector construction. ResearchGate. https://doi.org/10.13140/RG.2.2.18947.00809
Azhar, S. (2011). Building Information Modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadership and Management in Engineering, 11(3), 241–252.
Babbie, E. R. (2021). The practice of social research (15th ed.). Cengage Learning.
Bass, B. M. (1990). From transactional to transformational leadership: Learning to share the vision. Organizational Dynamics, 18(3), 19–31. https://doi.org/10.1016/0090-2616(90)90061-S
Boyatzis, R. E. (1982). The competent manager: A model for effective performance. New York: John Wiley & Sons.
Callistus, T., & Clinton, A. (2016). Evaluating barriers to effective implementation of project monitoring and evaluation in the Ghanaian construction industry. Procedia Engineering, 164, 389–394. https://doi.org/10.1016/j.proeng.2016.11.635
Callistus, T., & Clinton, A. (2018). The role of monitoring and evaluation in construction project management. In W. Karwowski & T. Ahram (Eds.), Intelligent Human Systems Integration (Vol. 722, pp. 571–582). Springer. https://doi.org/10.1007/978-3-319-73888-8_89
Chadee, A., Ali, H., Gallage, S., & Rathnayake, U. (2023). Modelling the implications of delayed payments on contractors' cash flows on infrastructure projects. Civil Engineering Journal, 9(1), 52–71. https://doi.org/10.28991/CEJ-2023-09-01-05
Chan, A. P. C., & Chan, A. P. L. (2004). Key performance indicators for measuring construction success. Benchmarking: An International Journal, 11(2), 203–221. https://doi.org/10.1108/14635770410532624
Cohen, L., Manion, L., & Morrison, K. (2018). Research methods in education (8th ed.). London: Routledge.
Creswell, J. W., & Creswell, J. D. (2018). Research design: Qualitative, quantitative, and mixed methods approaches (5th ed.). SAGE Publications.
Damoah, I. S., & Boateng, F. G. (2020). Performance appraisal systems and project delivery in the Ghanaian construction sector. Built Environment Project and Asset Management, 10(5), 785–800.
Danso, H., Frimpong, S., & Owusu, E. (2021). Barriers to the adoption of modern construction management tools in developing countries: Evidence from Ghana. Journal of Engineering, Design and Technology, 19(5), 1134–1151.
DeNisi, A. S., & Williams, K. J. (2018). Performance appraisal and performance management: 100 years of progress? Journal of Applied Psychology, 102(3), 421–433. https://doi.org/10.1037/apl0000085
Dillman, D. A., Smyth, J. D., & Christian, L. M. (2014). Internet, phone, mail, and mixed-mode surveys: The tailored design method (4th ed.). Hoboken, NJ: Wiley.
Field, A. (2018). Discovering statistics using IBM SPSS statistics (5th ed.). London: Sage Publications.
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in the construction of groundwater projects in developing countries: Ghana as a case study. International Journal of Project Management, 21(5), 321–326. https://doi.org/10.1016/S0263-7863(02)00055-8
Fugar, F. D. K., & Agyakwah-Baah, A. B. (2010). Delays in building construction projects in Ghana. Australasian Journal of Construction Economics and Building, 10(1–2), 103–116. https://doi.org/10.5130/ajceb.v10i1-2.1592
Gamil, Y., & Abd Rahman, I. (2021). Studying the relationship between causes and effects of poor communication in construction projects using the PLS-SEM approach. Journal of Facilities Management, 21(1), 102–148. https://doi.org/10.1108/JFM-04-2021-0039
George, D., & Mallery, P. (2019). IBM SPSS statistics 25 step by step: A simple guide and reference (15th ed.). Routledge.
Ghana Statistical Service. (2022). 2021 Population and housing census: Summary report of final results. Accra: Ghana Statistical Service.
Hatoum, M. B., & Nassereddine, H. (2024). Determining decision-making factors for technology adoption in the construction industry. In Industry 4.0 Transformation Towards Industry 5.0 Paradigm. IntechOpen. https://doi.org/10.5772/intechopen.1004365
Hinze, J. (2011). Construction safety (2nd ed.). Prentice Hall.
Hofstede, G. (2001). Culture's consequences: Comparing values, behaviors, institutions, and organizations across nations (2nd ed.). Thousand Oaks, CA: Sage.
Ibrahim, A., Zayed, T., & Lafhaj, Z. (2024). Enhancing construction performance: A critical review of performance measurement practices at the project level. Buildings, 14(7), 1988. https://doi.org/10.3390/buildings14071988
Kaplan, R. S., & Norton, D. P. (1996). The balanced scorecard: Translating strategy into action. Boston: Harvard Business School Press.
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). New York: John Wiley & Sons.
Khudzari, F., Rahman, R. A., Ayer, S. K., & Harun, A. T. (2023). Critical factors influencing construction technology adoption: A multivariate analysis. AIP Conference Proceedings, 2688(1), 030020. https://doi.org/10.1063/5.0111810
Longenecker, C. O., & Fink, L. S. (2017). Improving management performance in tough times. Journal of Management Development, 36(2), 240–252. https://doi.org/10.1108/JMD-08-2015-0110
Musarat, M. A., Alaloul, W. S., & Liew, M. S. (2021). Impact of inflation rate on construction projects budget: A review. Ain Shams Engineering Journal, 12(1), 407–414. https://doi.org/10.1016/j.asej.2020.04.009
Ngacho, C., & Das, D. (2014). A performance evaluation framework of development projects: An empirical study of Constituency Development Fund construction projects in Kenya. International Journal of Project Management, 32(3), 492–507. https://doi.org/10.1016/j.ijproman.2013.07.005
Nguyen, L., & Watanabe, T. (2017). The impact of project organizational culture on the performance of construction projects. Sustainability, 9(5), 781. https://doi.org/10.3390/su9050781
Njeru, C. M., & Kirui, D. C. (2022). Monitoring and evaluation practices and performance of Kenya National Highway Authority road construction projects in Nairobi City County, Kenya. Journal of Entrepreneurship & Project Management, 2(1), 11–27. https://doi.org/10.70619/vol2iss1pp11-27
Oakland, J. S. (2014). Total quality management and operational excellence: Text with cases (4th ed.). Routledge.
Ofori, G. (2012). Contemporary issues in construction in developing countries. London: Routledge.
Ogunbayo, B. F., Ramabodu, M. S., Adewale, B. A., & Ogundipe, K. E. (2024). Strategies for successful monitoring and evaluation practices in construction projects. 2024 International Conference on Science, Engineering and Business for Driving Sustainable Development Goals, 1–7. https://doi.org/10.1109/SEB4SDG60871.2024.10630137
Oladinrin, T. O., Ogunsemi, D. R., & Aje, I. O. (2013). Role of construction sector in economic growth: Empirical evidence from Nigeria. Journal of Construction in Developing Countries, 18(2), 93–109.
Onyia, U., Ani, I. S., & Nwankwo, U. F. (2024). Addressing the challenges towards the adoption of digital technologies in construction supply chain management. Discover Civil Engineering, 1(1), 118. https://doi.org/10.1007/s44290-024-00132-5
Owusu-Manu, D., Edwards, D. J., Badu, E., & Love, P. E. D. (2019). Key constraints to the adoption of innovative technologies in the Ghanaian construction industry. Engineering, Construction and Architectural Management, 26(4), 616–632.
Pallant, J. (2020). SPSS survival manual: A step-by-step guide to data analysis using IBM SPSS (7th ed.). London: McGraw-Hill Education.
Piwowar-Sulej, K. (2021). Organizational culture and project management methodology: Research in the financial industry. International Journal of Managing Projects in Business, 14(6), 1270–1289. https://doi.org/10.1108/IJMPB-08-2020-0252
Pittri, H., Godawatte, G. A. G. R., Esangbedo, O. P., Antwi-Afari, P., & Bao, Z. (2025). Exploring barriers to the adoption of digital technologies for circular economy practices in the construction industry in developing countries: A case of Ghana. Buildings, 15(7), 1090. https://doi.org/10.3390/buildings15071090
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Newtown Square, PA: PMI.
Sepasgozar, S. M. E., & Davis, S. (2018). Construction technology adoption cube: An investigation on process, factors, barriers, drivers, and decision makers using NVivo and AHP analysis. Buildings, 8(6), 74. https://doi.org/10.3390/buildings8060074
Shah, F. H., Bhatti, O. S., & Ahmed, S. (2023). A review of the effects of project management practices on cost overrun in construction projects. Engineering Proceedings, 44(1), 1. https://doi.org/10.3390/engproc2023044001
Shakeri, H., & Khalilzadeh, M. (2020). Analysis of factors affecting project communications with a hybrid DEMATEL-ISM approach. Heliyon, 6(8), e04430. https://doi.org/10.1016/j.heliyon.2020.e04430
Taber, K. S. (2018). The use of Cronbach's alpha when developing and reporting research instruments in science education. Research in Science Education, 48(6), 1273–1296. https://doi.org/10.1007/s11165-016-9602-2
Toor, S. R., & Ogunlana, S. O. (2010). Beyond the "iron triangle": Stakeholder perception of key performance indicators for large-scale public sector development projects. International Journal of Project Management, 28(3), 228–236. https://doi.org/10.1016/j.ijproman.2009.05.005
Turner, J. R. (2014). Handbook of project management (4th ed.). London: Routledge.
Wahab, A., Isaac, G., Ansah, A. O., Acquah, E., et al. (2025). Technological innovation and safety outcomes on Ghanaian construction sites: A role-based and project-type analysis. International Journal of Scientific Research in Science and Technology, 12(4), 634–654. https://doi.org/10.32628/IJSRST251335
Walker, A. (2015). Project management in construction (6th ed.). Chichester, UK: Wiley-Blackwell.
World Bank. (2020). Ghana economic update: Enhancing financial inclusion. Washington, DC: World Bank.
Yamane, T. (1967). Statistics: An introductory analysis (2nd ed.). New York: Harper & Row.

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.
Copyright (c) 2026 Ing. Japhet Korkwei Clottey (Author)